PI/PO to Integration Suite: how to triage hundreds of interfaces

A practical method for sorting every PI/PO interface into retire, migrate or redesign, so your migration plan is realistic from day one.

By the Klynexa integration team

Applies to
SAP PI/PO 7.x to SAP Integration Suite
Tools
Migration Assessment, Migration Tooling
Audience
Integration leads and architects

The problem

Most PI/PO landscapes have grown for ten years or more. When a migration starts, the interface list is long, ownership is unclear, and estimates swing wildly because every interface is treated as equally complex.

Step 1: Build a real inventory

Start from what actually runs, not from documentation. Pull message volumes for the last 6 to 12 months and match them to every integrated configuration. Interfaces with zero traffic are your first quick win.

  • Sender and receiver systems, adapters and protocols
  • Mapping type: graphical, XSLT, Java or ABAP
  • Monthly message volume and peak load
  • Business owner and criticality

Step 2: Sort every interface into one of three groups

  • Retire: no traffic, duplicates, or flows replaced by standard SAP cloud integrations. Confirm with the business owner, then switch off.
  • Migrate: standard adapters and graphical or XSLT mappings. SAP’s migration assessment and migration tooling handle much of this work, followed by testing.
  • Redesign: ccBPM or BPM processes, Java mappings, custom adapter modules and heavily customized flows. These need a new design, not a copy.

Step 3: Map the hard parts early

  • ccBPM and BPM: rebuild as iFlows, or move long-running human steps to SAP Build Process Automation.
  • Java mappings: rewrite as message mappings or Groovy scripts. Keep the test messages from PI/PO to compare results.
  • ABAP proxies: connect through the XI adapter in Cloud Integration, usually with minimal backend change.
  • On-premise systems: plan SAP Cloud Connector or Edge Integration Cell before the first wave, not during it.

Step 4: Plan waves

Wave 1 takes low-risk, high-volume “migrate” interfaces to build confidence and templates. Wave 2 covers the remaining standard flows. Wave 3 handles critical and redesigned flows with parallel runs and message comparison before cutover.

Result

Teams that triage first typically find a meaningful share of interfaces can be retired, the effort estimate becomes defensible, and the business sees early progress instead of a long silent build phase.